Six jobs are to be processed on two milling machines. All of them follow the same machine sequence. Determine the optimal job sequence and minimum total expected time from the data given below

              Job No.

1

2

3

4

5

6

Processing

Time(Min)

M/c 1

5

4

2

5

6

3

M/c 2

7

3

8

3

1

5

        