0 votes
41 views
asked in im&or by (215k points)

A project consists of 7 Jobs.  Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed.  Jobs D E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:

 

Time Estimates (Days)

Job

Optimistic

Pessimistic

Most Likely

A

3

7

5

B

7

11

9

C

4

18

14

D

4

12

8

E

4

8

6

F

5

19

12

G

2

6

4

Draw the network and determine the critical path, and its expected duration (Te). What is the probability of completing the project in Te days?  Also, determine the total & free slacks of all the jobs.

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...