        Table gives the different activities associated with a project and their durations. Draw the network diagram and determine the critical path. Also determine the critical path time.

Activity

Event

Duration

(in Day)

Beginning

i

Ending

j

A

1

2

47

B

2

3

43

C

1

3

80

D

1

4

33

E

4

7

33

F

1

5

21

G

5

8

37

H

1

8

50

I

3

6

22

J

6

9

22

K

9

11

86

L

8

10

22

M

10

11

22

N

11

12

21

O

12

13

63

P

7

11

15

                                                                    