      A small plant layout job consists of 10 steps. Their precedence relationships and activity times are identified as follows:

Step

A

B

C

D

E

F

G

H

I

J

Predecessor

-

-

-

A

B

B

C,F

D,G

E,H

C,F

Time (Hours)

9

13

16

18

19

8

11

9

26

35

      Draw the network and complete the forward and backward passes. What activities make up the critical path? Which activity has the most slack?                                                 