A job shop has received an order consisting of 7 different jobs. These are to be processed through a milling machine and a drilling machine. Processing time of each machine is given in the following table. suggest the optimum processing sequence. Prepare a Gantt chart and indicate the total time for completing the order. if no other order is processed simultaneously, what are the percentage utilization of milling and drilling machines?
Processing time in minutes in respective machines
|
Job name
|
A
|
B
|
C
|
D
|
E
|
F
|
G
|
Milling M/C
|
12
|
8
|
9
|
14
|
6
|
7
|
10
|
Drilling M/C
|
10
|
12
|
6
|
8
|
14
|
9
|
5
|