0 votes
62 views
asked in IM&OR by (215k points)

A job shop has 6 orders to be completed by a single turning centre. The processing times and due dates are as follows:                                                                                                         

Job

1

2

3

4

5

6

Processing time

3

2

9

4

2

4

Due date

17

21

5

12

15

24

Assume that all orders are ready for processing. Give a production schedule that minimizes the average flow time. Compare this schedule with one that minimizes tardiness (lateness)