A job shop incurs a cost of Rs. 60/- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with the following data.                                                                                       

Job

1

2

3

4

5

Processing time (days)

5

3

8

2

6

Due date (days)

10

12

20

9

8

      Which schedule will minimize the total cost? What is the minimum total cost?

      Which job (if any) fail to meet their due dates?