Four jobs are to be processed on a machine as per data listed in the table.
Job
|
Processing
Time (in days)
|
Due date
|
1
|
4
|
6
|
2
|
7
|
9
|
3
|
2
|
19
|
4
|
8
|
17
|
- If the Earliest Due Date (EDD) rule is used to sequence the jobs, the number of jobs delayed is
(a) 1 (b) 2 (c) 3 (d) 4
2. Using the Shortest Processing Time (SPT) rule, total tardiness is