The precedence relations and durations of jobs in a project are given below:

     

Job

Predecessors(s)

Duration (in days)

A

-

2

B

-

4

C

A

6

D

A

8

E

B,C

6

F

B,C

4

G

F

2

H

F

8

I

D,E,G

6

 

      (a) Draw the activity-on-arc project network

      (b) Determine all critical path(s) and their duration(s).

      (c) Which is the total float for jobs B and D                                                                                                  