- (a) A power generating station has a maximum demand of 20 MW. The daily load on the station is as follows.
Time
|
Load, MW
|
6 AM to 8 AM
8 AM to 12 NOON
12 NOON to 1 PM
1 PM to 5 PM
5 PM to 7 PM
7 PM to 9 PM
9 PM to 11 PM
11 PM to 6 AM
|
7
16
6
15
17
20
9
4
|
- Draw the load curve and load duration curve for the plant.
- Decide the capacity and number of units.
- Prepare the operating schedule of the units.
Determine the load factor, plant capacity factor and plant use factor of the station.