0 votes
153 views
asked in im&or by (215k points)
The type of schedule inherent in the material requirements planning (MRP) procedure is

(a) Forward schedule      

(b) Backward schedule

(c) Both backward and forward schedule

(d) Different from backward and forward schedule

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...