0 votes
44 views
asked in im&or by (215k points)
Weekly production requirements of a product are 1000 items. The cycle time of producing one product on a machine is 10 minutes. The factory works on two shift basis in which total available time is 16 hours. Out of the available lime about 25% is expected to be wasted on break downs, material unavailability and quality related problems. The factory works for 5 days in a week. How many machines are required to fulfill the production requirements?

                                                

(a) 2        (b) 3                 (c) 4         (d) 6

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...