 Time estimates of a project activity are

 top, optimistic time  = 10 days

  tml, most likely time = 15 days

  tpcs, pessimistic time  = 22 days

 Variance in days for this activity as per BETA  distribution is

 (a) 12        (b) 7       (c) 5        (d) 4
 

Please log in or register to answer this question.