  Earning in Rowan system

         Earning in 50% Halsey plan

            = R ´ Ta + p (Ts–Ta) R

         Where, R = hourly rate,

         Ta = actual completion time of task

         Ts= standard time of task

         p = percentage allowed

         Both Rowan system and 50% Halsey plane will provided the same earing when the actual time is          

         (a) Equal to standard time

         (b) Half the standard time

         (c) One-quarter of standard time

         (d) Twice the standard time