An 8-hour measurement study in a plant reveals that 320 number of units were produce(d) If idle time = 15% and performance rating = 120%, with allowance = 12% of normal time, the standard time per unit produced will be  

         (a) 1.823 minutes            (b) 1.714 minutes

         (c) 1.645 minutes            (d) 1.286 minutes