Manufacturing a product requires        processing on four machines A, B, C, and D in the order A–B–C–(d) The capacities of   four machines are A = 100, B = 110, C = 120 and D = 130 units per shift. If the       expected output is 90% of the system   capacity, then what is the expected output?

                                               

(a) 90 units                     (b) 99 units

(c) 108 units                   (d) 117 units