0 votes
73 views
asked in im&or by (215k points)

Consider the following sets of tasks to complete the assembly of an engineering component: The expected production rate is 3000 units per shift of 8 hour duration. The minimal number workstations that are needed to achieve this production level are:                                                           

Task

Time (in seconds)

Precedence

a

10

-

b

20

-

c

15

a

d

5

b

e

30

c

f

15

e

G

5

d

 

(a) 4        (b) 8        (c) 10            (d) 11      

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...