Consider the following steps which are involved in constructing a function analysis system technique of value engineering:

1. Find the critical path            

2. Prepare a function worksheet

3. Listing of functions

4. Diagram layout

Which of the following gives the correct sequence of steps?

(a) 1, 3, 2, 4                    (b) 2,1,3,4

(c) 4, 2, 3, 1                    (d) 3, 2, 4, 1