The uncertainty of duration time estimates in PERT described network?
0
votes
102
views
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
Which one of the following distributions provides information regarding the uncertainty of duration time estimates in PERT described network?
(a) Beta – distribution
(b) Normal distribution
(c) Poisson distribution
(d) Binomial distribution
ies-objectives-2
2016
im&or
pert&cpm
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
Related questions
0
votes
0
answers
Which one of the following is assumed for timing the activities in PERT network?
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2002
im&or
pert&cpm
0
votes
0
answers
For the PERT network shown in the given figure the probability of completing the project in 27 days is
asked
Dec 30, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
1994
im&or
pert&cpm
0
votes
0
answers
In PERT and CPM network the dummy activity
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2010
im&or
pert&cpm
0
votes
0
answers
A dummy activity is used in PERT network for:
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2013
im&or
pert&cpm
0
votes
0
answers
Which of the following is true with respect to a PERT network?
asked
Dec 31, 2017
in
im&or
by
chandu
(
215k
points)
ies-objectives-2
2012
im&or
pert&cpm
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.
Categories
All categories
GATE
(2k)
IES Objectives-1
(1.8k)
IES Objectives-2
(2.8k)
tom
(488)
md
(417)
som
(393)
material science
(345)
production
(703)
im&or
(472)
robotics
(1)
mechatronics
(4)
engg mechanics
(5)
IES Conventional-1
(655)
IES Conventional-2
(1.1k)
IAS Mains
(633)
IAS Prelims
(1.2k)
IES GS & Aptitude
(61)
Engineering Mathematics
(1)
Most popular tags
ies-objectives-2
gate
ies-objectives-1
production
iasprelims
ies-conventional-2
im&or
tom
fm
td
som
ies-conventional-1
iasmains
md
ppe
2009
2008
2014
2007
2005
10.4k
questions
274
answers
26
comments
15.3k
users
...