A capstan lathe is used to mass – produce in batches of 200, a particular component. The direct material cost is Rs 4 per piece the direct labour cost is Rs 3 per piece and the overhead costs are 400% of the labour costs. What is the production cost per piece?                                 

(a) Rs 19                         (b) Rs 23

(c) Rs 16                         (d) Rs 15