  A manufacturer’s master product schedule of product is given below:     

Period           Planned                    Week – 1

Week – 2               Week – 3

Planned        Production                    50                        100                          100

Week – 4              Week – 5            Week – 6

100                          150                     50

 

Each product requires a purchased component A in its sub – assembly. Before the start of week – 1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order for:

(a) 400 components in week - 1

(b) 400 components in week – 3

(c) 200 components in week – 1 and 200 components in week – 3

(d) 400 components in week – 5

Please log in or register to answer this question.