0 votes
52 views
asked in im&or by (215k points)
It is given that the’ actual demand is 59 units; a previous for cast 64 units and smoothening factor 0.3. What will be the forecast for next period, using exponential smoothing?                  

(a) 36.9 units                  (b) 57.5 units

(c) 60.5 units                  (d) 62.5 units

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...