Four technicians are required to do four different jobs. Estimates of time to complete every job as provided by the technicians are as below:

Technician

Hours to complete Job

Job1

Job2

Job3

Job4

A

20

36

31

27

B

24

34

45

22

C

22

45

38

18

D

37

40

35

28

      Assign the jobs to technician to minimize the total work-time.  State the steps taken in the algorithm used.