Find the sequence that minimizes the total elapsed time required to complete the following jobs. Each job is processes in the order ACB.
|
Processing times in hours
|
Job No.
Machine A
Machine B
Machine C
|
1
5
3
2
|
2
7
7
1
|
3
6
5
4
|
4
9
6
5
|
5
5
7
3
|
Determine the sequence of the jobs, makespan and idle time of machines. Illustrate the method of solution and assumptions taken.