Find the sequence that minimizes the total elapsed time required to complete the following jobs. Each job is processes in the order ACB.

 

 

Processing times in hours

Job No.

Machine A

Machine B

Machine C

1

5

3

2

2

7

7

1

3

6

5

4

4

9

6

5

5

5

7

3

Determine the sequence of the jobs, makespan and idle time of machines. Illustrate the method of solution and assumptions taken.