0 votes
86 views
asked in production by (215k points)

Find the sequence that minimizes the total elapsed time required to complete the following jobs. Each job is processes in the order ACB.

 

 

Processing times in hours

Job No.

Machine A

Machine B

Machine C

1

5

3

2

2

7

7

1

3

6

5

4

4

9

6

5

5

5

7

3

Determine the sequence of the jobs, makespan and idle time of machines. Illustrate the method of solution and assumptions taken.

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...