0 votes
68 views
asked in IM&OR by (215k points)
Which of the following can be solved by the Brown and Gibson procedure?

         (a) Transportation problem

         (b) CPM network

         (c) Site location problem

         (d) Product – mix problem

Please log in or register to answer this question.