0 votes
112 views
asked in IM&OR by (215k points)
In a time study experiment, observed time is 15 minutes, operator rating is 90,personal need allowance is 4%, fatigue allowance is 3%, contingency allowance for work is 3% and contingency allowance for delay is 2%. The total work content, in minutes, is _______.

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments