Which one of the following is NOT a decision taken during the aggregate production planning stage?                                                                                                                                               

      (a) Scheduling of machines

      (b) Amount of labour to be committed

      (c) Rate at which production should happen

     (d) Inventory to be carried forward

1 Answer

0 votes
answered by (1.2k points)
Correct answer is A

An aggregate plan determines the aggregate production levels, inventory levels and resource capacities over the planning horizon. The resource capacities such as workforce levels are determined assuming one aggregate unit of production.
All other options are objective of Aggregate Production Planning whereas option (A), Scheduling of machines is the objective of detailed Job shop Scheduling/operations scheduling. This answers which machine will be used to produce which product/job and when the products/jobs will be produced.
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...