The distribution of lead time demand for an item is as follows:                                                                                           

     

Led time demand

Probability

80

0.20

100

0.25

120

0.30

140

0.25

      The reorder level is 1.25 times the expected value of the lead demand. The service level is                      

      (a) 2.5%                                                              (b) 50%

      (c) 75%                                                               (d) 100