0 votes
160 views
asked in IM&OR by (215k points)

Arrival of machines for repair in a maintenance shop follows a Poisson distribution at a rate of one per 18 hours. The time to repair follows an exponential distribution with Mean Time “To Repair (MTTR) of 14 hours. If the productivity loss is Rs. 22,500 per hour, then the total expected loss of productivity due to machine breakdowns, in Rs., is                                                                                                               

      (a) 78,750                                                           (b) 1,01,250

      (c) 11,81,250                                                      (d) 14,17,500

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...