0 votes
57 views
asked in IM&OR by (215k points)

Differentiate between method study and motion analysis. How are they used in job design?

        The elemental times (in minutes) for 4 cycles of an operation using a time measuring device are presented below:

 

CYCLE TIME IN MINUTES

ELEMENTS

C1

C2

C3

C4

1

3.0

3.0

2.6

2.8

2

5.2

5.4

4.85

5.2

3

6.6

6.4

6.8

6.8

4

2.4

2.4

2.2

2.4

5

1.02

1.02

1.04

0.96

      Calculate standard time for the operation, if

  1. Elements 2 and 4 are machine dependent.
  2. For other elements, the operator is rated at 110%.
  3. Total allowances are 15% of the normal time.

Please log in or register to answer this question.

Related questions

0 votes
0 answers
asked Aug 23, 2017 in IM&OR by chandu (215k points)
0 votes
0 answers
asked Aug 23, 2017 in IM&OR by chandu (215k points)
0 votes
0 answers
Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

15.3k users

...