The gross head available to a hydraulic power plant is 100m. the utlised head in the runner of the hydraulic turbine is 72 m. if the hydraulic efficiency of the turbine is 90% the pipe friction head is estimated to be  

(a)20 m                        (b)18 m

(c) 16.2 m                    (d)1.8 m