0 votes
50 views
asked in im&or by (215k points)
An 8-hour measurement study in a plant reveals that 320 number of units were produce(d) If idle time = 15% and performance rating = 120%, with allowance = 12% of normal time, the standard time per unit produced will be  

         (a) 1.823 minutes            (b) 1.714 minutes

         (c) 1.645 minutes            (d) 1.286 minutes

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...