0 votes
70 views
asked in im&or by (215k points)
Manufacturing a product requires        processing on four machines A, B, C, and D in the order A–B–C–(d) The capacities of   four machines are A = 100, B = 110, C = 120 and D = 130 units per shift. If the       expected output is 90% of the system   capacity, then what is the expected output?

                                               

(a) 90 units                     (b) 99 units

(c) 108 units                   (d) 117 units

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...