0 votes
26 views
asked in im&or by (215k points)
edited by

 There are two machines $M_{1}$ and $M_{2}$ which process jobs A,B,C,D,E and F. the processing sequence for these jobs is  $M_{1}$ followed by $M_{2}$. Consider the following data in this regard:              

Process time required in minutes

Jobs              A   B    C     D    E     F

                   4    7    3     12   11     9

                   11  7   10      8    10    13

The processing sequence of jobs that would minimize the make span is:

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions