0 votes
116 views
asked in production by (215k points)

Following data refers to an automat and a centre lathe, which are being compared to machine  batch of parts in a manufacturing shop

 

         Automat

     Center Lathe

Machine Set-up Time I min

             120

             30

Machine Set-up Cost in Rs/min

             800

             150

Machining Time per piece in min

             2

             5

Machining Cost in Rs/min

             500

             100

Automat will be economical if the batch side exceeds

(a) 28        (b) 32         (c) 61           (d) 75

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.7k users

...