0 votes
34 views
asked in IM&OR by (215k points)
Consider the following steps in a line balancing problem:

            1. Apply an assignment heuristic to assign tasks to each work station.

            2. Identify the precedence requirements

            3. Calculate the required minimum number of work stations

            Which one of the following is the correct sequence of the above steps?

            (a) 2 – 3 – 1                 (b) 1 – 2 – 3

            (c) 2 – 1 – 3                 (d) 1 – 3 – 2

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...