0 votes
48 views
asked in IM&OR by (215k points)

There are three alternatives to meet the demand of a product

Alternative I :

Manufacture using a process P

Alternative II:

Manufacture using a process Q

Alternative III:

Buy the product from a vendor

The costs associated with each alternative is given below.

 cost

Alternative I

Alternative II

Alternative III

Fixed cost

Rs. 1,00,000

Rs. 1,90,000

 

Variable cost (per unit)

Rs. 75

Rs. 60

 

Purchase price (per unit)

 

 

Rs. 87.50

Alternative I is cheaper compared to alternative II when the demand is

      (a) 8500                                                              (b) above 8000

      (c) 6500                                                              (d) below 6000

 

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...