0 votes
52 views
asked in IM&OR by (215k points)

A job shop incurs a cost of Rs. 60/- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with the following data.                                                                                       

Job

1

2

3

4

5

Processing time (days)

5

3

8

2

6

Due date (days)

10

12

20

9

8

      Which schedule will minimize the total cost? What is the minimum total cost?

      Which job (if any) fail to meet their due dates?

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...