Six jobs arrived in a sequence as given below:
Job
Completion time
I
4
II
9
III
5
IV
10
V
6
VI
8
Average flow time (in days) for the above jobs using shortest Processing time rule is
(a) 20.83 (b) 23.16
(c) 125.00 (d) 139.00