0 votes
72 views
asked in IM&OR by (215k points)
In an assembly line for assembling toys, five workers are assigned tasks which take times of 10, 8, 6, 9 and 10 minutes respectively. The balance delay for line is                                                                                                                    

      (a) 43.3%                        (b) 14.8%                    (c) 1.0%                          (d) 16.3%

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.6k users

...