0 votes
75 views
asked in production by (215k points)
Consider the following operations and time required on a multispindle automatic machine to

 produce a  particular job

   1. Turning   : 1.2 minutes

   2. Drilling   : 1.6 minutes

   3. Forming   :  0.2 minute

   4. Parting   : 0.6 minute

  The time required to make one piece (cycle time) will be

 (a) 0.6 minute      (b) 1.6 minutes     (c) 3.6 minutes     (d) 0.9 minutes

Please log in or register to answer this question.

Welcome to Q&A discussion forum, where you can ask questions and receive answers from other members of the community.

10.4k questions

274 answers

26 comments

14.7k users

...