A project is composed to eleven activities. The time estimates are given below:

Activity

to

tp

tm

1 – 2

7

17

9

1 – 3

10

60

20

1 – 4

5

15

10

2 – 5

50

110

65

3 – 6

50

90

55

4 – 7

40

68

48

5 – 8

5

15

10

6 – 8

20

52

27

7 – 8

30

50

40

  1. Draw the network diagram of project.
  2. Calculate slack time for each node.
  3. Determine critical path