Time study of an operator with a performance rating of 120% yield a time of 2 minutes. If the allowances of 10% of the total available time are to be given, then what is the standard time of operation?

            (a) 2.00 minutes          (b) 2.40 minutes

            (c) 2.64 minutes          (d) 2.67 minutes